Glenview Ice Center
The below flythrough animation from Williams Architects, as of October 2018, includes an updated increase of 2400 square feet to the overall size of the building.
The animation shows energy-efficient translucent windows. The video gives you a 360 view of the exterior, and then brings you inside the first and second floors, showcasing additions in square footage to the lobby and main corridor for better flow of foot traffic. The final view is the studio rink from the second floor.
ice center renovations
Replace outdated electrical, plumbing, sewer lines and HVAC system
Improve accessibility for persons with disabilities
Update fire suppression system
Improve building envelope to address leaking and energy inefficiencies
Add complete new sheet of ice, taking the complex up to 2.5 total sheets
Address other space and parking needs
glenview community ice center timeline
-
Architect, Exhibit Designer and Engineer Selection
Completed May 2018
-
Owner’s Representative Selection
Completed May 2018
-
Construction Manager Selection
Completed May 2018
-
Bid Package #1 Awarded – Ice Systems
Completed February 2019
-
Bid Package #2 Awarded – Site utilities, site demolition and building excavation, building demolition, site electrical, asphalt paving and site concrete
Completed February 2019
-
Bid Package #3 Issued
Completed April 2019
-
Construct the Project
Ongoing Spring/Fall/Winter 2019
-
Anticipated Opening of Main Sheet of Ice
Summer 2020
-
Facility Grand Opening
Fall 2020