The Glenview Park District opens bidding to respectable and honorable companies and corporations and reviews each bid thoroughly before making vendor decisions.

There are no open bids at this time.

bids archive

On Thursday, February 25, 2021, 3 bids were received for Waste Disposal and Recycling Services.  At the March, 18, 2021 Park Board meeting, this work was awarded to Lakeshore Recycling Systems, of Morton Grove, IL in the amount of $116,382.61. Click here to review the Bid Tabulation Sheet.

On Thursday, January 23, 2020, 3 bids were received for Seasonal Landscape Maintenance Services.  At the February 27, 2020 Park Board meeting, this work was awarded to ILT Vignocci of Wauconda, IL in the amount of $143,254.65 per year, for the next three years of service.

Closing Date: 02/27/2020

review tabulation sheet

On Tuesday, February 18, 2020, four bids were received for the Glenview Community Ice Center Furniture project. At the February 27, 2020 Park Board meeting the project was awarded to Henricksen of Itasca, Illinois in the amount of $96,539.81.

Closing Date: 02/18/2020

review tabulation sheet

On Friday, September 27, 2019, 3 bids were received for Camp Bus Transportation. At the October 24, 2019 Park Board meeting, this bid was awarded to First Student based out of Naperville, IL for $72,449.

Closing Date: 11/13/2019

review tabulation sheet

On Friday, September 27, 2019, 5 bids were received for the Shirt and Uniform Bid. At the October 24, 2019 Park Board meeting, this bid was awarded to Ad Wear of Texas based out of Houston, TX for $38,712.39 and All Star Custom Apparel based out of Henrietta, New York for $1,503.28.

Closing Date: 11/13/2019

review tabulation sheet

On Monday, September 23, 2019, five bids were received for Seasonal Brochure Printing and Mailing Services. At the October 24, 2019 Park Board meeting, this project was awarded to Paulson Press, Inc. of Elk Grove Village, IL, the lowest, qualified bidder for this project.

Closing Date: 10/24/2019

review tabulation sheet

On Thursday, August 29, 2019, four bids were received for the Community Park West Sports Field Drainage project. At the September, 19, 2019 Park Board meeting, this work was awarded to Lenny Hoffman Excavating, of Wilmette, IL for $368,870.

Closing Date: 09/19/2019

review tabulation sheet

On Thursday, November 29, 2018, eight (8) bids were received for the Park Center – HVAC Replacement Project. At the December 13, 2018 Park Board meeting, this work was awarded to Amber Mechanical Contractors, Inc. of Alsip, IL in the amount of $432,000.00. Click here to review the Bid Tabulation Sheet.

On Thursday, August 30, 2018, three bids were received for the Gallery Park asphalt pathway repairs. This work was awarded to the low bidder, Allstar Asphalt, of Wheeling, IL for $21,745.40 for the base bid items. Click here to review the Bid Tabulation Sheet.

On Thursday, August 2, 2018, two bids were received for the Grove Asphalt Shingle Roof Replacement. At the August 23, 2018 Park Board meeting, this work was awarded to Select Construction Group, LLC of Elgin, IL for $88,000. Click here to review the Bid Tabulation Sheet.

On Thursday, March 1, 2018, four bids were received for Parking Lot Pavement Maintenance. At the March 22, 2018 Park Board meeting, this work was awarded to Patriot Maintenance Inc., of Mundelein, IL  for $26,847. Click here to review the Bid Tabulation Sheet.

On Thursday, March 1, 2018, two bids were received for Basketball / Tennis Projects 2018. At the March 22, 2018 Park Board meeting, this work was awarded to First Impression Inc., of Franklin Park, IL for $68,370. Click here to review the Bid Tabulation Sheet.

On Thursday, March 1, 2018, five bids were received for the installation of Plant Material. At the March 22, 2018 Park Board meeting, this work was awarded to the Americana Landscape Group, of Elgin, IL  for $82,429.40. Click here to review the Bid Tabulation Sheet.

On Thursday, February 8, 2018, six bids were received for the Hoffman School Playground Installation. At the February 22, 2018 Park Board meeting, this work was awarded to Elanar Construction in the amount of $62,395. Click here to review the Bid Tabulation Sheet.

On Thursday, October 5, 2017, three bids were received for the 2018 Summer Bus Services. At the November 16, 2017 Park Board meeting, this work was awarded to First Student in the amount of $79,155.52. Click here to review the Bid Tabulation Sheet.

On Thursday, October 5, 2017, eight bids were received for the Shirts, Uniforms, Bags and Apparel. At the November 16, 2017 Park Board meeting, this work was awarded to Sharp Sports in the amount of $32,165.76, Sunburst Sportswear in the amount of $11,478.44 and Arena Sports in the amount of $11,187.40. Click here to review the Bid Tabulation Sheet.

On Wednesday, December 13, 2017, six bids were received for the Cole Park Fieldhouse Concrete Foundation. At the December 21, 2017 Park Board meeting, this work was awarded to Copenhaver Construction Co., of Gilberts, IL in the amount of $77,322. Click here to review the Bid Tabulation Sheet.

On Thursday, June 29, 2017, six bids were received for the 2017 Concrete Sidewalk Projects. At the July 27, 2017 Park Board meeting, this work was awarded to Elanar Construction Co., of Chicago, IL in the amount of $120,033. Click here to review the Bid Tabulation Sheet.

On Thursday, May 25, 2017, two bids were received for the renovation of the Park Center Health and Fitness showers.  At the June 22, 2017 Park Board meeting, this work was awarded to Construction Consulting & Disbursement Services, of Morton Grove, IL in the amount $ $101,190.  Click here to review the Bid Tabulation Sheet.

On Tuesday, June 20, 2017, eleven bids were received for the Wagner Farm Drainage Project. This work was awarded to DiMeo Bros. for the Base Bid work, and Team Reil for the Alternate work. Click here to review the Bid Tabulation Sheet.

On Thursday, May 4, 2017, five bids were received for the installation of sports field lighting at Flick Park. At the May 25, 2017 Park Board meeting, this work was awarded to Barton Electric Inc., of Trenton, IL  in the amount $375,705. Click here to review the Bid Tabulation Sheet.

On Thursday, March 2, 2017, three bids were received for the installation of plant material. At the March 23, 2017 Park Board meeting, this work was awarded to Elanar Construction, of Chicago, IL in the amount $100,840. Click here to review the Bid Tabulation Sheet.

On Thursday, March 2, 2017, seven bids were received for the installation of a drainage system at Diederich Park. At the March 23, 2017 Park Board meeting, this work was awarded to Elanar Construction, of Chicago, IL in the amount $38,041.50.  Click here to review the Bid Tabulation Sheet.

On Thursday, March 2, 2017, three bids were received for the installation of shade Shelters. At the March 23, 2017 Park Board meeting, this work was awarded to Elanar Construction, of Chicago, IL in the amount $95,740. Click here to review the Bid Tabulation Sheet.

On Wednesday, February 22, 2017, four bids were received for the Shirts, Uniforms, Bags and Apparel bid. At the March 23, 2017 Park Board meeting, this work was awarded to Sharp Sports of Shorewood, IL in the amount $26,863.29.  Click here to review the Bid Tabulation Sheet.

On Wednesday, February 22, 2017, three bids were received for the Summer Bus Service. At the March 23, 2017 Park Board meeting, this work was awarded to First Student of Naperville, IL in the amount $73,312.50.  Click here to review the Bid Tabulation Sheet.

On Thursday, February 2, 2017, three bids were received for tree removal and pruning services. At the March 23, 2017 Park Board meeting, this work was awarded to Lucas Landscaping & Design Co., of Deerfield, IL.  Click here to review the Bid Tabulation Sheet.

On Friday, January 27, 2017, four bids were received for Basketball and Tennis projects. At the March 23, 2017 Park Board meeting, this work was awarded to 10-S Court Solutions, of Lake Forest IL in the amount $82,463. Click here to review the Bid Tabulation Sheet.

On Thursday, January 26, 2017, six bids were received for Seasonal Landscape Maintenance Services. At the March 23, 2017 Park Board meeting, this work was awarded to ILT Vignocchi, of Wauconda, IL in the amount of $103,761 for the next three years of service. Click here to review the Bid Tabulation Sheet.

On Thursday, January 26, 2017, seven bids were received for the Henking School Playground project. At the March 23, 2017 Park Board meeting, this work was awarded to Hacienda Landscaping of Plainfield, IL in the amount $71,748. Click here to review the Bid Tabulation Sheet.

On Thursday, January 26, 2017, three bids were received for the Park Center Wood Gym Floor Refinishing project. At the February 23, 2017 Park Board meeting, this work was awarded to Manico Flooring, of McHenry, IL in the amount $59,559. Click here to review the Bid Tabulation Sheet.

On Thursday, January 12, 2017, four bids were received for the Glenview Prairie Club Platform Tennis Court Expansion project.  At the February 23, 2017 Park Board meeting, this work was awarded to Elanar Construction, of Chicago, IL in the amount $537,440.  Click here to review the Bid Tabulation Sheet.

On Thursday, September 1, 2016, four bids were received for the Asphalt and Concrete Sidewalk Projects. At the September 22, 2016 Park Board meeting, this work was awarded to Allstar Asphalt , of Wheeling, IL in the amount $55,405. Click here to review the Bid Tabulation Sheet.

At the August 25, 2016 Park Board meeting, the board approved the purchase of one bunker rake and one 84 inch trim mower from Reinders of Sussex, Wisconsin in the amount of $46,718.53. Click here to review the Bid Tabulation Sheet.

At the June 23, 2016 Park Board meeting, the board accepted bids for (4) Cross Trainers from LifeFitness, Rosemont, IL in the amount of $13,069.92 and (3) Cross Trainers from Direct Fitness Solutions, Mundelein, IL in the amount of $15,297.50. Click here to review the Bid Tabulation Sheet.

On Friday, June 3, 2016, two bids were received for the Baseball Backstop Replacement project. At the June 23, 2016 Park Board meeting, this work was awarded to Action Fence Contractors, of Mundelein, IL in the amount of $91,427.72. Click here to review the Bid Tabulation Sheet.

At the May 26, 2016 Park Board meeting, this work was awarded to the sole bidder, Continental Construction, of Evanston, IL in the amount of $43,312.

On Thursday, May 05, 2016, four bids were received for the Community Park West Lighting Improvements. At the May 26, 2016 Park Board meeting, this work was awarded to Barton Electric, of Trenton, IL in the amount of $439,500. Click here to review the Bid Tabulation Sheet.

On Thursday, March 31, 2016, three bids were received for the Ice Center Renovations bid. At the April 28, 2016 Park Board meeting, the board accepted the bid from Redmond Construction of Glenview, IL in the amount of $72,583. Click here to review the Bid Tabulation Sheet.

On Monday, April 4, 2016, two bids were received for the Summer Bus Service bid. At the April 28, 2016 Park Board meeting, the board accepted the bid from Olson Transportation of Gurnee, IL in the amount of $46,475.50. Click here to review the Bid Tabulation Sheet.

On Friday, February 26, 2016, four bids were received for the Westbrook Backstop Replacement project.    At the April 28, 2016 Park Board Meeting, the Board of Park Commissioners decided not to move forward with this project. Click here to review the Bid Tabulation Sheet.

On Friday, March 4, 2016 eight bids were received for the Summer T-shirt, Uniform, Bag and Apparel bid. At the March 24, 2016 Park Board meeting, the board accepted bids from the following companies: Roselynn Fashions; Sportsdecals Inc.; Sunburst Sportswear; Arena Sports USA, and Marathon Sportswear totaling $23,930.17. Click here to review the Bid Tabulation Sheet.

On Thursday, March 3, 2016 four bids were received for the Cunliff Tennis Court Drainage project. At the March 24, 2016 Park Board meeting, this work was awarded to Elanar Construction, of Chicago, IL in the amount of $26,188 for the Base Bid items and Alternates #1a, 1c, 1d, & 1e. Click here to review the Bid Tabulation Sheet.

On Thursday, March 3, 2016 four bids were received for the Parking Lot Pavement Marking and Crack Fill project. The Glenview Park District has awarded this work to the lowest bidder, Patriot Pavement Maintenance, of Des Plaines, IL in the amount of $10,334, for the Base Bid items and Alternates #1a & 1b. Click here to review the Bid Tabulation Sheet.

On Friday, February 26, 2016, six bids were received for the Shade Structure Installation project.  At the March 24, 2016 Park Board meeting, this work was awarded to Elanar Construction, of Chicago, IL in the amount of $28,480  for the Base Bid items. Click here to review the Bid Tabulation Sheet.

On Friday, February 26, 2016, seven bids were received for Concrete Sidewalk Installation. At the March 24, 2016 Park Board meeting, this work was awarded to Continental Construction Company, Inc., of Evanston, IL in the amount of $73,960  for the Base Bid items and Alternates #1 & 2. Click here to review the Bid Tabulation Sheet.

On Thursday, February 25, 2016, one bid was received for the Gallery Park Rubber Surfacing Installation. At the March 24, 2016 Park Board meeting, this work was awarded to Elanar Construction, of Chicago, IL in the amount of $55,147.50 for the Base Bid items and Alternates #1-3. Click here to review the Bid Tabulation Sheet.

On Thursday, February 25, 2016, three bids were received for Basketball/Tennis projects. At the March 24, 2016 Park Board meeting, this work was awarded to 10-S Court Solutions, of Lake Forest, IL in the amount of $153,288  for the Base Bid items and Alternates #1,2 & 5. Click here to review the Bid Tabulation Sheet

On Thursday, February 25, 2016, three bids were received for Landscape Plant Material Installation. At the March 24, 2016 Park Board meeting, this work was awarded to Elanar Construction, of Chicago, IL in the amount of $178,691  for the Base Bid items and Alternate #1. Click here to review the Bid Tabulation Sheet.

On Thursday, February 25, 2016, four bids were received for the Grove Parking Lot Solar Lighting. At the March 24, 2016 Park Board meeting, this work was awarded to Utility Dynamics Corporation, of Oswego, IL in the amount of $38,700  for the Base Bid items. Click here to review the Bid Tabulation Sheet.

The District opened bids for the Park Center Splash Roof and the HVAC Replacements on January 20, 2016. A total of ten bids were received. At the February 25, 2016 board meeting, the Glenview Park District Board of Commissioners awarded the bid to A1 Roofing. Click here to review the Bid Tabulation Sheet.